In order to keep pace with the growing needs of the community, the City of Houston Department of Public Works and Engineering will be improving the safe sidewalks in the areas described below. The contractor for this project is Metro City Construction, L.P. Work started on August 5, 2009, and is scheduled to end on January 31, 2010. You may not see any activity by the contractor for several weeks after the construction time has begun. This is due to the contractor getting prepared to perform work which includes procurement of materials and equipment, setting up staging areas or working in other areas in the project.
A detailed description and contact information is listed below.
- WBS No. N-00610A-00H4-4 & N-00610A-00H5-4
- Project Description: Safe Sidewalk Program H4 & H5 Project
- Construction Cost: $841,950.56
Streets involved in construction:
Street Name |
To |
From |
Kelly |
Hwy 59 N. |
Wayne |
Lavender |
Cavalcade |
Pardee |
Lucerne |
Tautenhahn |
Little York |
Suburban |
Winfield |
Mt. Houston |
Winfield |
River Trail |
Swan River |
Foy |
Hartwick |
Hopper |
Kingwood |
Sweetstem |
High Valley |
Hickory |
Winter |
Dart |
Victoria |
Volley |
Arlington |
13th East |
Cortlandt |
Beverly |
13th West |
Dorothy |
Herkimer |
33rd |
Link |
Bacchus |
Roy |
Center |
Schuler |
Cornish |
Radcliff |
TC Jester |
39th |
Yale |
Main |
Port |
Laredo |
Waxahachie |
Shepherd |
13th |
12th |
Heights |
15th |
14th |
Nordling |
Canino |
Little York |
Solo |
Providence |
Coke |
Patterson |
I.H. 10 East |
Washington |
Terry |
Malvern |
Egypt |
St. Charles |
Navigation |
Canal |
The contractor is required to provide residents written notification, via door hangers, 72 hours prior to construction beginning on your street.
If you have questions about the construction phase please contact the Construction Management and Inspection Project Manager or the City of Houston Project Manager listed above. If the issue is not resolved to your satisfaction please contact the City of Houston Managing Engineer listed above or Tim Lincoln, Senior Assistant Director, Construction Branch at (713) 837-7074 or e-mail at tim.lincoln@cityofhouston.net. |