CitizensNet Banner

November 4, 2009

Notification of Capital Improvement Plan Construction Project in
a portion of District G and Westpark Sanitary Sewer station

In order to keep pace with the growing needs of the community, the City of Houston through the Department of Public Works and Engineering will be improving the sanitary sewer system and rehabilitating the Westpark Sanitary Sewer Lift Station in the areas described below. The contractor for this project is Metro City Construction, L.P. and work started on Monday, October 12, 2009, and is scheduled to end on January 15, 2011. You may not see any activity by the contractor for several weeks after the construction time has begun. This is due to the contractor getting prepared to perform work which includes procurement of materials and equipment, setting up staging areas or working in other areas in the project.

A detailed description and contact information are listed below.

  • WBS No.: R-002011-0052-4
  • Project Description: Neighborhood Sewer System Improvements
  • Key Map Grid (492F, 493N, 529D)
  • Construction Cost:  $1,993,943.60

Streets involved in construction:

STREET NAME FROM TO
Peden Avenue Montrose Blvd Stanford Street
Bomar Street Montrose Blvd Grant Street
Bomar Street Grant Street Hopkins Street
Bomar Street Whitney Street Morgan Street
Damon Court Grant Street Crocker Street
Crocker Street Bomar Street Damon Court
Willard Street  Montrose Blvd Grant Street
Willard Street Stanford Street Hopkins Street
Welsh Street Stanford Street Hopkins Street
Stanford Street Drew Street Welsh Street
Stanford Street Willard Street Peden Street
Haskell Avenue Coppage Street Schuler Street
Pickens Avenue Alley    
Westpark Lift Station No. 3 At Westpark Drive and Beltway 8 

The contractor is required to provide residents written notification, via door hangers, 72 hours prior to construction beginning on your street.

If you have questions about the construction phase please contact the City of Houston Project Manager listed above. If the issue is not resolved to your satisfaction please contact the City of Houston Managing Engineer listed above or Tim Lincoln, Senior Assistant Director, Construction Branch at (713) 837-7074 or e-mail at tim.lincoln@cityofhouston.net.