CitizensNet Banner

November 10, 2008

Notification of Capital Improvement Plan Construction
Project in Richmond Avenue area

In order to keep pace with the growing needs of the community, the City of Houston through the Department of Public Works and Engineering will be improving/expanding the streets listed in NSR 455 project within the limits described below. The contractor for this project is Total Contracting Limited and work will start on Monday, December 1, 2008 and is scheduled to end on February 23, 2010.  You may not see any activity by the contractor for several weeks after the construction time has begun. This is due to the contractor getting prepared to perform work which includes procurement of materials and equipment, setting up staging areas or working in other areas in the project.

A detailed description and contact information is listed below.

WBS No. N-000378-0001-4
Project Description: Neighborhood Street Reconstruction (NSR) 455
Construction Cost:  $6,588,489.00

Streets involved in construction:

Street

 

From Street

To Street

KEY MAP

 

               
Bonnie Brea Street   Dunlavy Street Yupon Street 492Z,493W  
           
Bonnie Brea Street   Graustark Street Mt. Vernon Street 493W  
           

Castle Court

 

Dunlavy Street

Graustark Street

492Z,493W

 

 

 

 

 

 

 

 

 

 

 

 

Dunlavy Street

 

Richmond Avenue

US 59

492Z

 

 

 

 

 

 

 

 

 

 

 

 

Graustark Street

 

Richmond Avenue

US 59

493W

 

 

 

 

 

 

 

 

 

 

 

 

Lexington Avenue

 

Hazard Street

Dead-end

492Z

 

 

 

 

 

 

 

 

 

 

 

Mandell Street

 

Richmond Avenue

US 59

492Z

 

 

 

 

 

 

 

 

 

 

 

 

Miramar Street

 

Graustark Street

Mt. Vernon Street

493W

 

 

 

 

 

 

 

 

 

 

 

 

Mt. Vernon  Street

 

Miramar

US 59

493W

 

 

 

 

 

 

 

 

 

 

 

 

Norfolk Avenue

 

Dunlavy Street

Mandel Street

492Z

 

 

 

 

 

 

 

 

 

 

 

 

Sul Ross Avenue

 

Driscoll Street

Dead-end

492Z

 

 

 

 

 

 

 

 

 

 

 

 

West Main

 

Yoakum Boulevard

Montrose Boulevard

493W

 

 

 

 

 

 

 

 

 

 

 

 

Yupon Street

 

Richmond Avenue

US 59

493W

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Construction Firm: Total Contracting Limited.
Construction Firm Project Manager: Pierre G. Merhi @ 713-995-8595.
Project Manager:  Anh H. Hunter, P.E.,   713-837-0393,   anh.hunter@cityofhouston.net
Managing Engineer: JoAnne M. Kamman, P.E.   713-837-7398, joanne.kamman@cityofhouston.net

The contractor is required to provide residents written notification, via door hangers, 72 hours prior to construction beginning on your street. Periodic updates of the construction schedule will be sent out using CitizensNet.

If you have questions about the construction phase please contact the City of Houston Project Manager listed above. If the issue is not resolved to your satisfaction please contact the City of Houston Managing Engineer listed above or J. Timothy Lincoln, P.E., Senior Assistant Director, Construction Branch at (713) 837-7074 or e-mail at tim.lincoln@cityofhouston.net

Register for CitizensNet or go to www.houstontx.gov and scroll down to CitizensNet logo.

Change your email address or Update your record

To prevent your email service provider from marking a CitizensNet message as spam,
please add Mayor.Bill.White@cityofhouston.net to your address book.

Disclaimer: All information, excluding your e-mail address, is generally subject to public disclosure
under the Texas Public Information Act (See Chapter 552 of the Texas Government Code).

Thank you for your continued interest in the CitizensNet E-Newsletter.
Mailing Address:  City of Houston | P.O. Box 1562 | Houston, Texas 77251
City Hall Address:  City of Houston | 901 Bagby | Houston, Texas 77002