CitizensNet Banner

July 21, 2009

Notification of Capital Improvement Plan
Construction Project in the Timber Oaks West area

In order to keep pace with the growing needs of the community, the City of Houston 

Department of Public Works and Engineering will be improving/replacing the water lines in Timber Oaks as described below. The contractor for this project is D.L. Elliott Enterprises, Inc. The work started Monday, July 20, 2009 and is scheduled to end on March 8, 2010.  You may not see any activity by the contractor for several weeks after the construction time has begun. This is due to the contractor getting prepared to perform work which includes procurement of materials and equipment, setting up staging areas or working in other areas in the project.

A detailed description and contact information is listed below.

  • WBS No.: S-000035-00M7-4
  • Project Description: Water Line Replacement in Timber Oaks West Area
  • Construction Cost:  $955,269.05

Streets involved in construction:

Street

From street

To Street

Shadow Bend

Timberwood

Raritan

Shadow Bend

Londonderry

Timber Oaks

Shadow Bend

Eddystone

Chatterton

Shadow Bend

Mayfield

Hazelhurst

Raritan

Shadowdale

Shadow Bend

Timberwood

Shadowdale

Shadow Bend

Timber Oaks

Shadowdale

Shadow Bend

Haddington

Shadowdale

Shadow Bend

Londonderry

Shadowdale

Shadow Bend

Chatterton

Shadowdale

Shadow Bend

Eddystone

Shadowdale

Shadow Bend

Hazelhurst

Shadowdale

Shadow Bend

Ivyridge

Shadowdale

Shadow Bend

Mayfield

Shadowdale

Shadow Bend

Wisterwood

Shadow Oaks

Brinwood

Shadowdale

Shadow Oaks

Raritan

Springwell

Timber Oaks

Loop

Prism

Timber Oaks

Loop

Triway

Timber Oaks

Loop

Shadeland

Shadow Oaks

Brinwood

Oak Wilde Ct.

Shadow Oaks

Cul - De - Sac

Brinwood Ct.

Brinwood

Cul - De - Sac

Laurenhurst

Shadowdale

Cul - De - Sac

  • Contractor Firm: D.L. Elliott Enterprises, Inc.
  • Contractor Contacts: Dwayne Schroeder @ 281-277-4414
  • Construction Manager Firm:  LJA Engineering & Surveying, Inc.
  • Construction Project Manager:  Larry J. Brown @ 713-451-0214, ljbrown@ljaengineering.com
  • Project Manager:  Anh H. Hunter, P.E.,   713-837-0393,   anh.hunter@cityofhouston.net
  • Managing Engineer: JoAnne M. Kamman, P.E., 713-837-7398, joanne.kamman@cityofhouston.net

The contractor is required to provide residents written notification, via door hangers, 72 hours prior to construction beginning on your street.

If you have questions about the construction phase please contact the City of Houston Project Manager listed above. If the issue is not resolved to your satisfaction please contact the City of Houston Managing Engineer listed above or J. Timothy Lincoln, P.E., Senior Assistant Director, Construction Branch at (713) 837-7074 or e-mail at tim.lincoln@cityofhouston.net.