CitizensNet Banner

August 12, 2008

Notification of Capital Improvement Plan Construction Project in White Heather area

In order to keep pace with the growing needs of the community, the City of Houston through the Department of Public Works and Engineering will be improving the wastewater lines, water lines, storm sewers, streets, sidewalks and roadside ditches in the area described below. The contractor for this project is Angel Brothers, Ent., Ltd. and work will start on August 25, 2008 and is scheduled to end on February 25, 2010 . You may not see any activity by the contractor for several weeks after the construction time has begun. This is due to the contractor getting prepared to perform work which includes procurement of materials and equipment, setting up staging areas or working in other areas in the project

A detailed description and contact information is listed below.

WBS No.: M-000262-0001-4

Project Description: White Heather Storm Sewer Improvements Segment I

Project Location: Key Map Grid 572S

Construction Cost: $8,786,305.27

Streets involved in construction:

Street Name To From

West Anderson Rd. White Heather Dr . Bathurst Dr .

Oakside Dr . White Heather Dr . Bathurst Dr .

High Point Ln. White Heather Dr . Bathurst Dr .

Curly Oaks Dr . White Heather Dr . Bathurst Dr .

Brownstone Ln. White Heather Dr . Bathurst Dr .

Rosebud Dr. White Heather Dr . Bathurst Dr .

Knottynold Ln. White Heather Dr . Bathurst Dr .

Smooth Oak Ln. White Heather Dr . Bathurst Dr .

White Heather Dr . West Anderson Rd. West Fuqua

Bathurst Dr . West Anderson Rd. West Fuqua

Construction Firm: Angel Brothers, Ent., Ltd.

Construction Firm Project Manager : Kevin Guy, (281) 421-5721

City of Houston Project Manager: Jeff Masek, P.E., (713) 837-7369

Jeff.masek@cityofhouston.net

City of Houston Managing Engineer: JoAnne Kamman, P.E., (713) 837-7208

Joanne.kamman@cityofhouston.net

The contractor is required to provide residents written notification, via door hangers, 72 hours prior to construction beginning on your street. Periodic updates of the construction schedule will be sent out using CitizensNet.

If you have questions about the construction phase please contact the City of Houston Project Manager listed above. If the issue is not resolved to your satisfaction please contact the City of Houston Managing Engineer listed above or Tim Lincoln, Senior Assistant Director, Construction Branch at (713) 837-7074 or e-mail at tim.lincoln@cityofhouston.net.