November 6, 2012 Sewer Repair Scheduled at Taft and Hawthorne The City of Houston Department of Public Works and Engineering (PWE) is scheduled to repair a sanitary sewer line and manhole, followed by street restoration, at the Taft and Hawthorne intersection. This work is tentatively scheduled for mid-November to early December 2013, weather permitting. PWE received information regarding a large depression in the street and a thorough investigation determined the sewer line cracked and is susceptible to infiltration and erosion. Barricades were placed to ensure public safety. Note: Once work starts there may be some limited traffic delays. This project is being managed by PWE Public Utilities Division, WasteWater Operations Branch. For questions contact Alvin Wright at alvin.wright@houstontx.gov or 832.395.2455. To learn more about PWE, visit www.publicworks.houstontx.gov.
|