Fannin - Bates to Holcombe, University - Travis Street to Main Street, Main Street - Sunset to Holcombe
CIP
M-0260
BEGIN
04.01.2008
END
450 days -- May 2009
COST
$11,542,284
CONTRACTOR
Texas Sterling Construction
DESCRIPTION
The project consists of approximately 7,270 linear feet of 30-inch, 24-inch, 16-inch, 12-inch, and 8-inch water lines, 1050 linear feet of 24-inch storm sewer, 4,400 linear feet of 54-inch, 48-inch, 24-inch, 18-inch, 16-inch, and 12-inch sanitary sewer rehabilitation and total concrete roadway reconstruction with curb and gutter.
The project, which is designed to provide drainage improvements within the Harris Gully watershed and reduce the flood potential to the Texas Medical Center, Rice University, Hermann Park, and surrounding areas, will last for 450 calendar days and be done in phases. This project is anticipated to be completed by May, 2009. Typically, work hours will be between 7:00am to 7:00pm six days a week.