KIRBY DRIVE STORM SEWER IMPROVEMENTS

ZIP 77005, 77098
STREETS Kirby Drive, from Brays Bayou to Southwest Freeway
CIP
  • M-0771-01-3 (Phase I, Braes Bayou to Dorrington, COMPLETE)
  • M-0771-02-3 (Phase II, Dorrington to Swift, COMPLETE)
  • M-0771-03-2 (Phase III, Swift to Robinhood)
  • M-0771-04-2 (Phase IV, Robinhood to U.S. 59)
BEGIN
  • 07.26.2004 (Phase I)
  • 03.06.2006 (Phase II)
  • Fiscal Year 2006 (Phase III, estimated)
  • Sept. 2007 (Phase IV, estimated)
END
  • 630 days (Phase I)
  • 425 days (Phase II)
COST
  • $12,853,470.84 (Phase I)
  • $12,960,334.00 (Phase II)
  • $14,089,638.80 (Phase III, estimated)
  • $12,840,310.00 (Phase IV, estimated)
CONTRACTOR
  • Texas Sterling Construction (Phase I)
  • Total Contracting Limited (Phase II)
  • Reytec Construction Co. Inc. (Phase III)
  • None selected (Phase IV)
DESCRIPTION Project needed to alleviate localized flooding. More details at www.swmp.org.