www.houstontx.gov > Construction Projects > Neighborhood Street Reconstructin 440A

NEIGHBORHOOD STREET RECONSTRUCTION 440A

ZIP 77025
STREETS Basson, McDermed, Nenana, Oboe, O'Meara, Silverwood, Woodcraft, Woodfin, Woodfix, Woodhaven, Woodshire, Woodwind
CIP N-0373-02-3
BEGIN 9.29.03
END 560 days
COST $6,700,353.50
CONTRACTOR Total Contracting Limited
DESCRIPTION Project provides design / construction for paving with curbs, gutters and sidewalks or with open ditches as determined by resident petition. Improves residential streets throughout the City and enhances the quality of life in neighborhoods.

NSR440A Map