General area bounded by Holmes, Scott, Bellfort, and Hwy. 288
CIP
M-0217-01-3
BEGIN
10.10.2006
END
348 days
COST
$5,325,195.12
CONTRACTOR
E.P. Brady
DESCRIPTION
The project consists of construction of approx. 627-linear ft of 4-ft X 2-ft reinforced concrete box storm sewer. Approx. 11,329-linear ft of 18-in thru 78-in diameter reinforced concrete storm pipe and ditch culverts with ditch regrading. The roadway pavement will be reconstructed full width with asphalt overlay and concrete curb and gutter. The project includes the construction of a detention basin between Mariah and Bassett. There is 2,649-linear ft of 8-in diameter sanitary sewer replacement along Brandon and 853-linear ft of 8-in diameter water line replacement at various locations.