Dairy Ashford Paving and Drainage (Memorial to Buffalo Bayou) WBS #: N-100023-0001-3

Overview of the Project: A complete reconstruction of a major thoroughfare.  Project is planned to widen existing four lanes to six lanes, make major upgrades to the storm sewers, and will replace utilities, sidewalks and street lights as needed.

The current milestones for this project are:

Design Completion Date: May 11, 2020 (Expected)
Construction Advertisement Date: October 23, 2020 (Expected)
Construction Contract Award Date: January 13, 2021 (Expected)
Begin Construction: Spring 2021

None of the project design has been approved yet.  The project is still early in design.  Once the design consultant has produced preliminary drawings, the District G office will host a public design input community meeting where the consultant and Houston Public Works will present the plan and answer questions from constituents.  Comments are usually taken via a survey for a month or so, then a re-draft is started to correct / revise items requested by the public. 

Questions/Additional Information: