Kirkwood #3 Lift Station

Information Regarding R-000536-0021-3 Diversion and Abandonment of Kirkwood #3 Lift Station to Harvest Moon Lift Station:

(1) Letter from former Council Member Oliver Pennington: (1st & 2nd pages of attachment, number 4 below)

(2) Map of Proposed Construction Path: (3rd page of attachment, number 4 below)

Proposed Milestones:

  • Design Completion: April 25, 2016 (anticipated)
  • Construction Advertisement: October 14, 2016 (anticipated)
  • Construction Contract Award Date: February 22, 2017 (anticipated)
  • Construction would be sometime in mid-2017 (anticipated)

Updated Milestones (1-6-17):

  • Design Completion Date: August 28, 2017 (Expected)
  • Construction Advertisement Date: March 30, 2018 (Expected)
  • Construction Contract Award Date: July 24, 2019 (Expected)
  • Targeted CIP Construction FY: 2019

(3) The Public Meeting will be held Thursday, June 11, 2015, from 6:30 pm to 8:00 pm at the Briarwood School, located at 12207 Whittington, Houston, TX 77077

(4) Kirkwood Lift Station Attachment (.pdf)

(5) PowerPoint Presentation from 6-11-15 Public Meeting (.pdf)