In order to keep pace with the growing needs of the community, the City of Houston Department of Public Works and Engineering will be improving/replacing the water lines in Briargrove Park as described below. The contractor for this project is RWL Construction, Inc. The work will start on Monday, July 7, 2009 and is scheduled to end on April 11, 2010. You may not see any activity by the contractor for several weeks after the construction time has begun. This is due to the contractor getting prepared to perform work which includes procurement of materials and equipment, setting up staging areas or working in other areas in the project

A detailed description and contact information is listed below.

WBS No.: S-000035-00V7-4
Project Description: Water Line Replacement in Briargrove Park
Construction Cost: $1,607,803.66

Streets involved in construction:

Street Name From street To Street

Briar Hill Drive / Shady River Drive

W. Sam Houston Parkway

Bayou Glen

Briar Drive / Briar Park Drive

Briar Hill Drive

Sugar Hill Drive

Bayou Glen Road

Briar Drive

Briarpark Drive

Green Tree Road

Briar Hill Drive

Briarpark Drive

Pine Forest Road

Briar Hill Drive

Briarpark Drive

Candlewood Drive

Briar Hill Drive

Briarpark Drive

Holly Springs Drive

Briar Hill Drive

Briarpark Drive

Sugar Hill Drive

Briar Hill Drive

Briarpark Drive

Lynbrook Hollow

W. Sam Houston Parkway

Loop

Briar Hill Drive

Lynbrook Hollow

Shady River Road

Briar Brook Drive

Bordley Drive

Sugar Hill Drive

Briar Brook Drive

Sugar Hill Drive

Briar Drive


Construction Firm: RWL Construction, Inc.
Contractor Contacts: Mario Aguilar @ 281-831-5892 and Darrell Stevens @ 281-831-5866
Project Manager:

Anh H. Hunter, P.E., 713-837-0393

  anh.hunter@cityofhouston.net
   
Managing Engineer: JoAnne Kamman, P.E.  (713) 837-7208
  joanne.kamman@cityofhouston.net

The contractor is required to provide residents written notification, via door hangers, 72 hours prior to construction beginning on your street. Periodic updates of the construction schedule may be sent out using CitizensNet.

If you have questions about the construction phase please contact the City of Houston Project Manager listed above. If the issue is not resolved to your satisfaction please contact the City of Houston Managing Engineer listed above or J. Timothy Lincoln, P.E., Senior Assistant Director, Construction Branch at (713) 837-7074 or e-mail at tim.lincoln@cityofhouston.net