CitizensNet Banner

July 21, 2009

Notification of Capital Improvement Plan
Construction Project in the Forest West and Cole Creek area

In order to keep pace with the growing needs of the community, the City of Houston Department of Public Works and Engineering will be improving the water lines in the area described below. The contractor for this project is D. L. Elliott Enterprises, Inc. and work started on July 9, 2009, and is scheduled to end on April 15, 2010.  You may not see any activity by the contractor for several weeks after the construction time has begun. This is due to the contractor getting prepared to perform work which includes procurement of materials and equipment, setting up staging areas or working in other areas in the project.

A detailed description and contact information is listed below.

  • This project consists of approximately 29,470 linear feet of 4-inch, 6-inch and 8-inch diameter water lines, valves, and appurtenances.
  • WBS No.:  S-000035-00V9-4
  • Project Description:  Water Line Replacement in Forest West and Cole Creek
  • Construction Cost:   $1,610,813.63

Streets involved in construction:

Street Name
To
From

Greenmont

Autumn Forest

Lost Forest

Silver Forest

Autumn Forest

Deep Forest

Autumn Forest

Lost Forest

Deep Forest

Spruce Forest

Lost Forest

Birchmont

Birchmont

Lost Forest

Spruce Forest

Spruce Forest

Birchmont

Deep Forest

Birchmont

Spruce Forest

Deep Forest

Lost Forest

Golden Forest

Greenmont

Deep Forest

Golden Forest

Silver Forest

Cole Creek

Langfield Road

Burr Oak

Chinaberry

W. Tidwell Road

Cole Creek

Inkberry

Chinaberry

Burr Oak

Shurmard

Inkberry

Cole Creek

Bitternut

Inkberry

Cole Creek

Willow Oak

Inkberry

Cole Creek

Black Gum

Inkberry

END

Black Oak

Inkberry

Cole Creek

Anaqua

Inkberry

Cole Creek

Burr Oak

W. Tidwell Road

Cole Creek

Pine Vista

Knotty Wood

END

Pine Cove Ct.

Pine Vista

Loop

Drowsy Pine

Langfield Road

Pine Bark

Pine Bark

Drowsy Pine

Loop

Pine Bark

Pine Grove

Drowsy Pine

Drowsy Pine

Knotty Wood

Pine Grove

Pine Grove Ct.

Langfield Road

Cul-de-sac

Pine Grove

Langfield Road

Drowsy Pine

Knotty Wood

Pine Grove

Pine Vista

Autumn Arbor

Arbor Vitae

Lost Forest

  • Construction Firm: D. L. Elliott Enterprises, Inc.
  • Construction Firm Project Manager: Dwayne Schroeder, 281-277-4414
  • Construction Management and Inspection (CM&I) Firm: S&B Infrastructure, Ltd.
  • CM&I Project Manager: HoJin Lim, P.E., 713.845.5440, hlim@sbinfra.com 
  • CM&I Project Inspector: James R. Thompson, 281-684-1711
  • City of Houston Project Manager: Nevzat Gokmen, P.E., 713-837-0609, Nevzat.Gokmen@cityofhouston.net
  • City of Houston Managing Engineer: Joe L. Smith, P.E., 713-837-0946, Joe.Smith@cityofhouston.net

The contractor is required to provide residents written notification, via door hangers, 72 hours prior to construction beginning on your street. 

If you have questions about the construction phase please contact the Construction Management and Inspection Project Manager or the City of Houston Project Manager listed above. If the issue is not resolved to your satisfaction please contact the City of Houston Managing Engineer listed above or Tim Lincoln, Senior Assistant Director, Construction Branch at (713) 837-7074 or e-mail at tim.lincoln@cityofhouston.net.